Contract Ledger
Every disclosed AI compute, colocation, hosting, power and equipment contract, one row per disclosure, read from the SEC filing it appeared in. Nulls mean the filing did not say. Nothing is estimated.
Contracts
15
15 from filings
Disclosed value
$5.27B
sum of stated totals, live
Capacity
1.20 GW
sum of stated MW, live
GPUs
8,464
where a count was stated
Providers
5
parties delivering
Latest filing
May 26, 2026
most recent disclosure
Customer concentration · by provider · top 8
Dell Marketing L.P.3 contracts
$5.10B · —top customer 55%
- IE US Hardware 4 Inc.$2.80B
- IE CA Leasing Ltd.$2.30B
Disclosures · 15
| Filed | Provider | Customer | Kind | Site | MW | GPUs | Term | Total value | Annual | Status | Source |
|---|---|---|---|---|---|---|---|---|---|---|---|
| May 26, 2026 | Dell Marketing L.P. | IE US Hardware 4 Inc. backstop: IREN Limited | GPU cloud capacity | Childress, Texas | — | — | — | $1.60B | — | Amendedverified | 8-K |
excerptOn May 19, 2026, IE US Hardware 4 Inc. (“IE US Hardware”), a wholly owned subsidiary of IREN Limited (the “Company”), and Dell Marketing L.P. (“Dell”) entered into purchase documentation (the “Dell Purchase Agreement”) pursuant to which Dell will supply to IE US Hardware GPUs and ancillary products and services (“GPUs”) for an aggregate purchase price of approximately $1.6 billion payable in installments within 30 days of each tranche shipping.Report an issue with this row | |||||||||||
| Mar 4, 2026 | Dell Canada Inc. | IE CA Leasing Ltd. backstop: IREN Limited | Equipment purchase | — | — | — | — | $2.30B | — | Definitiveverified | 8-K |
excerptOn March 4, 2026, IE CA Leasing Ltd. (“IE CA Leasing”), a wholly owned subsidiary of IREN Limited (the “Company”), and Dell Canada Inc. (“Dell Canada”) entered into purchase documentation (the “Dell Canada Purchase Agreement”) pursuant to which Dell Canada will supply to IE CA Leasing GPUs and ancillary products and services, scheduled to be delivered in phases during the second half of 2026, for an aggregate purchase price of approximately $2.3 billion payable in installments within 30 days of each tranche shipping.Report an issue with this row | |||||||||||
| Mar 4, 2026 | Dell Marketing L.P. | IE US Hardware 4 Inc. backstop: IREN Limited | Equipment purchase | — | — | — | — | $1.20B | — | Definitiveverified | 8-K |
excerptOn March 4, 2026, IE US Hardware 4 Inc. (“IE US Hardware”), an indirect wholly owned subsidiary of the Company, and Dell Marketing L.P. (“Dell USA”) entered into purchase documentation (the “Dell USA Purchase Agreement” and, together with the Dell Canada Purchase Agreement, the “Dell Purchase Agreements”) pursuant to which Dell USA will supply to IE US Hardware GPUs and ancillary products and services, scheduled to be delivered in phases during the second half of 2026, for an aggregate purchase price of approximately $1.2 billion payable in installments within 30 days of each tranche shipping.Report an issue with this row | |||||||||||
| Jul 7, 2025 | NVIDIA | IREN Limited | Equipment purchase | Prince George | — | 2,400 | — | — | — | Expandedverified | 8-K |
excerptBlackwell GPUs procured – 1.3k B200s & 1.1k B300s to be installed at Prince George over the coming months, lifting total fleet to 4.3k NVIDIA GPUs and unlocking next-gen training and inference at scaleReport an issue with this row | |||||||||||
| Jul 3, 2025 | NVIDIA | IREN Limited | Power supply | Prince George, BC | — | 2,400 | — | $130.00M | — | Amendedverified | 8-K |
excerptIREN today announced the purchase of 2.4k next-generation NVIDIA Blackwell B200 and B300 GPUs for ~$130m, including fit-out costs. ... The order (1.3k B200 and 1.1k B300 GPUs) will be installed over the coming months at IREN's Prince George, BC campusReport an issue with this row | |||||||||||
| Apr 4, 2025 | not stated | IREN Limited | Power supply | West Texas | 600 MW | — | — | — | — | Amendedauto 0.9 | 6-K |
excerptNew 600MW grid connection agreement signed ... This month, we secured an additional 600MW of grid-connected capacity, reflecting years of groundwork and bringing our total secured power capacity in West Texas to 2.75GW.Report an issue with this row | |||||||||||
| Mar 17, 2025 | AEP Texas Inc. | IREN Limited | Power supply | Sweetwater 2 | 600 MW | — | — | — | — | Amendedauto 0.9 | 6-K |
excerptOn March 17, 2025, IREN Limited (the “Company”) released a press release announcing the signing of a 600MW grid connection agreement with AEP Texas Inc. ... The Company expects to pay $4.1 million in non-refundable connection costs and $26.9 million in refundable deposits over the next 12 months. The project has an expected energization date in late 2027.Report an issue with this row | |||||||||||
| Sep 16, 2024 | NVIDIA | Undisclosed (Iris Energy Limited (dba IREN)) | Power supply | — | — | 1,080 | — | $43.90M | — | Amendedverified | 6-K |
excerptOn September 16, 2024, Iris Energy Limited (dba IREN) (the “Company”) announced its purchase of an additional 1,080 NVIDIA H200 GPUs to expand its AI Cloud Services business. ... The Company is purchasing 1,080 of the latest-generation NVIDIA H200 GPUs for $43.9m, with delivery and commissioning expected during 4Q 2024.Report an issue with this row | |||||||||||
| Aug 28, 2024 | IREN | Poolside | GPU cloud capacity | — | — | — | — | — | — | Amendedverified | 6-K |
excerpt · extension termsAI Cloud Services • 816 NVIDIA H100 GPUs, servicing multiple customers o AI Cloud Services revenue continues to scale o Launching Childress GPU pilot in H2 2024 o Poolside recently extended contract, expected to roll-off August 30, 2024: Consolidating clusters with [...] Extension: Contract recently extended; expected to roll-off August 30, 2024 Report an issue with this row | |||||||||||
| Jun 6, 2024 | IREN | Poolside AI | GPU cloud capacity | — | — | 504 | — | — | — | Expandedverified | 6-K |
excerpt816 NVIDIA H100 GPUs operating ... 504 GPUs contracted with Poolside AIReport an issue with this row | |||||||||||
| May 15, 2024 | IREN | Poolside AI | GPU cloud capacity | Prince George data center | — | 504 | — | — | — | Amendedverified | 6-K |
excerptAI Cloud Services revenue of $0.6 million, following the commissioning of 248 NVIDIA H100 GPUs during the quarter for our customer, Poolside AI ... Upsized (doubled to 504 GPUs) and extended our AI Cloud Services agreement with Poolside AIReport an issue with this row | |||||||||||
| May 6, 2024 | IREN | Poolside | GPU cloud capacity | — | — | 504 | — | — | — | Expandedverified | 6-K |
excerptAI Cloud Services ... 816 NVIDIA H100 GPUs ... Upsized (doubled to 504 GPUs) and extended AI cloud services agreement with PoolsideReport an issue with this row | |||||||||||
| Apr 8, 2024 | IREN | Poolside AI SAS | GPU cloud capacity | — | — | 504 | 4 mo | — | — | Expandedverified | 6-K |
excerpt · extension termsIREN has upsized and extended its AI cloud services agreement with poolside, more than doubling the contracted cluster size from 248 to 504 NVIDIA H100 GPUs. The contract is for an additional 4-month term commencing mid-April, 2024, with an extension option for a further 2 months at the customer’s election. Extension: 2-month extension option at customer's election Report an issue with this row | |||||||||||
| Mar 6, 2024 | IREN | poolside | GPU cloud capacity | Prince George, BC, Canada | — | — | 3 mo | — | — | Expandedverified | 6-K |
excerpt · extension termsContract secured with leading AI company, poolside, following rigorous customer testing requirements ... Initial 3-month term and extension option for an additional 3-months at the customer's election Extension: Extension option for an additional 3 months at customer's election Report an issue with this row | |||||||||||
| Mar 6, 2024 | NVIDIA | IREN | GPU cloud capacity | — | — | 568 | — | — | — | Expandedverified | 6-K |
excerptTripling AI cloud services business ... Fast-tracking AI cloud services business to 816 NVIDIA H100 GPUs with the purchase of 568 additional GPUs ... Delivery and commissioning of additional GPUs expected during Q2 2024Report an issue with this row | |||||||||||
Rows marked auto were extracted by a model and not yet reviewed; the excerpt under each row is the verbatim passage the figures came from. Confidence is the extractor's own estimate.