Contract Ledger

Every disclosed AI compute, colocation, hosting, power and equipment contract, one row per disclosure, read from the SEC filing it appeared in. Nulls mean the filing did not say. Nothing is estimated.

Contracts
9
9 from filings
Disclosed value
$18.60B
sum of stated totals, live
Capacity
1.11 GW
sum of stated MW, live
GPUs
—
where a count was stated
Providers
4
parties delivering
Latest filing
Jun 9, 2026
most recent disclosure
Reset

Customer concentration · by provider · filtered

Applied Digital5 contracts
$7.60B · 610 MWtop customer 68%
  • Undisclosed$5.20B
  • Base Electron, Inc.$2.40B
  • Oracle200 MW
  • a U.S.-Based Investment Grade Hyperscaler200 MW
$4.00B · 150 MWtop customer 100%
  • CoreWeave, Inc.$4.00B
APLD ELN-03 LLC1 contract
$4.00B · 150 MWtop customer 100%
  • CoreWeave, Inc.$4.00B
APLD ELN-02 LLC2 contracts
$3.00B · 200 MWtop customer 100%
  • Coreweave, Inc.$3.00B

Disclosures · 9

FiledProviderCustomerKindSiteMWGPUsTermTotal valueAnnualStatusSource
Jun 9, 2026Applied DigitalUndisclosed (CoreWeave)Colocation leasePolaris Forge 1, Building 3—————Amendedverified8-K
excerpt
Applied Digital also entered into a Memorandum of Understanding with CoreWeave on June 5, 2026, to assign the lease with CoreWeave for Building 3 at the Polaris Forge 1 campus to a CoreWeave subsidiary, if that subsidiary achieves an investment grade credit rating.
Report an issue with this row
Jun 9, 2026Applied Digital CorporationUndisclosed (U.S. based high investment-grade hyperscaler)Colocation leaseDelta Forge 2 Campus210 MW—15 yr$5.20B—Amendedverified8-K
excerpt · extension terms
The agreement covers 210 MW of critical IT load under a 15-year take-or-pay structure with renewal options, representing approximately $5.2 billion in base-term contracted revenue, or approximately $12.7 billion if all renewal options are exercised over a 30-year total term.

Extension: Renewal options; total term up to 30 years with total revenue ~$12.7B

Report an issue with this row
Mar 10, 2026Applied DigitalOraclePower supplyPolaris Forge 2, Harwood, North Dakota200 MW————Amendedverified8-K
excerpt
The Issuer intends to use the net proceeds from the offering to fund the development and construction of 200 megawatts of critical IT load at Polaris Forge 2, its AI Factory campus in Harwood, North Dakota currently leased to Oracle
Report an issue with this row
Mar 4, 2026Applied Digital CorporationBase Electron, Inc.
backstop: Applied Digital Corporation
Financing————$2.40B$2.40BAmendedverified8-K
excerpt
In connection with and as partial consideration for the Company’s entry into the Guarantee, Base Electron has agreed to issue to Applied Digital 10% of Base Electron’s outstanding equity. ... Applied Digital’s maximum potential exposure under the Guarantee is effectively limited by the obligations of Base Electron under the Design-Build Agreement, which provides for an anticipated total contract price of approximately $2.4 billion, subject to Applied Digital’s right to limit those obligations by terminating the Guarantee under the circumstances set forth in Item 1.01 of this Current Report on Form 8-K. ... the payment by the Company of a termination fee equal to either $50 million (if paid by August 1, 2026 and Base Electron is current in its payments to B&W) or $100 million.
Report an issue with this row
Nov 12, 2025Applied Digitala U.S.-Based Investment Grade HyperscalerColocation leasePolaris Forge 2 campus, Harwood, North Dakota200 MW————Amendedverified8-K
excerpt · extension terms
The Polaris Forge 2 campus has leased 200 MW of critical IT capacity, currently under construction, to a U.S.-Based Investment Grade Hyperscaler, which also holds the first right of refusal for an additional 800 MW of critical IT load at that campus

Extension: First right of refusal for an additional 800 MW of critical IT load at the same campus.

Report an issue with this row
Oct 9, 2025APLD ELN-02 LLCCoreweave, Inc.Colocation lease9663 87th Avenue SE, Ellendale, ND (Polaris Forge 1, ELN Building 02)100 MW————Amendedverified8-K
excerpt
"Coreweave Building 2 Lease" means that certain Datacenter Lease for the property located at 9663 87th Avenue SE, Ellendale, ND, dated as of May 28, 2025, by and between APLD ELN-02 LLC, a Delaware limited liability company, as landlord, and Coreweave, Inc., a Delaware corporation, as tenant. ... the Company's previously disclosed lease with a hyperscaler for the first 100 MW data center located at the Company's 400 MW Ellendale, North Dakota datacenter campus ("Polaris Forge 1")
Report an issue with this row
Aug 29, 2025APLD ELN-02 C LLCCoreWeave, Inc.Colocation leasePolaris Forge 1 Campus, Ellendale, North Dakota150 MW—15 yr$4.00B—Amendedverified8-K
excerpt
on August 28, 2025, APLD ELN-02 C LLC, a subsidiary of the Company, ... Forge 1 (“Building 4”), a 150MW data center to be constructed by the Company. ... The total contract value for the initial approximately fifteen (15)-year term of the Building 4 Lease is expected to be approximately $4.0 billion.
Report an issue with this row
Jun 2, 2025APLD ELN-02 LLCCoreWeave, Inc.Colocation leaseEllendale Campus, North Dakota (Building 2)100 MW—15 yr$3.00B—Definitiveverified8-K
excerpt · extension terms
On May 28, 2025, APLD ELN-02 LLC and APLD ELN-03 LLC ... each entered into a datacenter lease ... with CoreWeave, Inc. ... The first lease is for the full capacity of Building 2, the Company’s 100MW data center that is currently under construction (“Building 2”) ... The total contract value, for the initial approximately fifteen (15)-year term, (i) for the Building 2 Datacenter Lease is expected to be approximately $3 billion

Extension: Three 5-year extension options.

Report an issue with this row
Jun 2, 2025APLD ELN-03 LLCCoreWeave, Inc.Colocation leaseEllendale Campus, North Dakota (Building 3)150 MW—15 yr$4.00B—Definitiveverified8-K
excerpt · extension terms
On May 28, 2025, APLD ELN-02 LLC and APLD ELN-03 LLC ... each entered into a datacenter lease ... with CoreWeave, Inc. ... The second lease is for the full capacity of Building 3, a 150MW data center that is also under construction (“Building 3”) ... The total contract value, for the initial approximately fifteen (15)-year term ... (ii) for the Building 3 Datacenter Lease is expected to be approximately $4 billion

Extension: Three 5-year extension options.

Report an issue with this row

Rows marked auto were extracted by a model and not yet reviewed; the excerpt under each row is the verbatim passage the figures came from. Confidence is the extractor's own estimate.