Contract Ledger
Every disclosed AI compute, colocation, hosting, power and equipment contract, one row per disclosure, read from the SEC filing it appeared in. Nulls mean the filing did not say. Nothing is estimated.
Contracts
1
1 from filings
Disclosed value
$0
sum of stated totals, live
Capacity
600 MW
sum of stated MW, live
GPUs
—
where a count was stated
Providers
1
parties delivering
Latest filing
Mar 17, 2025
most recent disclosure
Customer concentration · by provider · filtered
Disclosures · 1
| Filed | Provider | Customer | Kind | Site | MW | GPUs | Term | Total value | Annual | Status | Source |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Mar 17, 2025 | AEP Texas Inc. | IREN Limited | Power supply | Sweetwater 2 | 600 MW | — | — | — | — | Amendedauto 0.9 | 6-K |
excerptOn March 17, 2025, IREN Limited (the “Company”) released a press release announcing the signing of a 600MW grid connection agreement with AEP Texas Inc. ... The Company expects to pay $4.1 million in non-refundable connection costs and $26.9 million in refundable deposits over the next 12 months. The project has an expected energization date in late 2027.Report an issue with this row | |||||||||||
Rows marked auto were extracted by a model and not yet reviewed; the excerpt under each row is the verbatim passage the figures came from. Confidence is the extractor's own estimate.