Nscale
privateBackers
No backer on file. That means no tracked fund's portfolio or Form D names this company — not that it is unbacked.
Contracts as provider
No filing on file discloses Nscale as the party delivering capacity, hosting, power or equipment.
Contracts as customer
4 disclosures · 160 MW · $3.46B| Filed | Provider | Kind | Site | MW | GPUs | Term | Total | Status | Source |
|---|---|---|---|---|---|---|---|---|---|
| Sep 9, 2026 | WhiteFiber | Colocation lease | — | 40 MW | — | 10 yr | $865.00M | Definitiveverified | 8-K |
excerpt · extension termsDec 2025 Nscale anchor contract 40 MW IT load / ~$865M TCV ... Anchored by a 10-year, 40 MW IT load agreement with Nscale, with expansion potential beyond the initial deployment. Extension: Expansion potential beyond the initial deployment. Report an issue with this row | |||||||||
| Jun 10, 2026 | WhiteFiber, Inc. | Colocation lease | NC-1 | 40 MW | — | 10 yr | $865.00M | Definitiveverified | 8-K |
excerpt · extension termsSigned 10-year, 40MW IT load agreement with Nscale representing ~$865M TCV Extension: Potential expansion toward ~2x initial deployment by end of 2027; Nscale receives priority notification rights for future site capacity. Report an issue with this row | |||||||||
| Jan 26, 2026 | WhiteFiber, Inc. | Colocation lease | NC-1 | 40 MW | — | 10 yr | $865.00M | Amendedverified | 8-K |
excerptSigned 10 - year, 40 MW colocation agreement with Nscale ($865M TCV) ... NC - 1: NSCALE ANCHOR CONTRACT Customer IT Load 40 MW Term 10 Years • Modified gross lease with expense pass - through • Retrofit development enables faster speed to market and lower cost • Initial deployment expected to be operational by mid - 2026 • Nscale receives priority notification rights for future site capacity • Project - level financing expected for 1Q 2026 Total Contract Value (1) $865MReport an issue with this row | |||||||||
| Dec 18, 2025 | Enovum NC-1 Bidco, LLC | Colocation lease | NC-1 Facility, Madison, North Carolina | 40 MW | — | 10 yr | $865.00M | Amendedverified | 8-K |
excerptThe initial Service Order provided pursuant to the Services Agreement covers 40 megawatts (“MW”) of information technology load, to be deployed in two 20 MW phases, at the NC-1 Facility and represents an expected $865 million in total contracted revenue over the initial 10-year term, including contractual annual rate escalators and non-recurring installation services.Report an issue with this row | |||||||||