Contract Ledger
Every disclosed AI compute, colocation, hosting, power and equipment contract, one row per disclosure, read from the SEC filing it appeared in. Nulls mean the filing did not say. Nothing is estimated.
Contracts
5
5 from filings
Disclosed value
$15.73B
sum of stated totals, live
Capacity
410 MW
sum of stated MW, live
GPUs
—
where a count was stated
Providers
5
parties delivering
Latest filing
Aug 10, 2026
most recent disclosure
Customer concentration · by provider · filtered
$8.50B · —top customer 100%
- CoreWeave Compute Acquisition Co. VIII, LLC$8.50B
Morgan Stanley & Co. LLC1 contract
$3.51B · 260 MWtop customer 100%
- Galaxy Helios Data Centers II LLC$3.51B
$3.10B · —top customer 100%
- CoreWeave Financing DDTL V, LLC$3.10B
$53.00M · 150 MWtop customer 100%
- Soluna DV Wind SponsorCo, LLC$53.00M
Disclosures · 5
| Filed | Provider | Customer | Kind | Site | MW | GPUs | Term | Total value | Annual | Status | Source |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Aug 10, 2026 | Morgan Stanley | Riot Platforms, Inc. | Financing | — | — | — | — | $573.00M | — | Amendedauto 1.0 | 8-K |
excerptFinancing: $573 million interim financing facility provided by Morgan Stanley to fund initial development costs while the investment-grade credit backstop is finalized.Report an issue with this row | |||||||||||
| Jul 28, 2026 | Morgan Stanley & Co. LLC | Galaxy Helios Data Centers II LLC backstop: Galaxy Helios II LLC | Financing | Dickens County, Texas | 260 MW | — | — | $3.51B | — | Definitiveverified | 8-K |
excerptOn July 28, 2026, Galaxy Helios Data Centers II LLC (“Issuer”), an indirect wholly owned subsidiary of Galaxy Digital Inc. (the “Company”), completed its previously announced private offering (the “Offering”) of 9.875% Senior Secured Notes due 2031 (the “Notes”). ... The aggregate principal amount of Notes sold in the Offering was $3,507,000,000.Report an issue with this row | |||||||||||
| May 18, 2026 | Morgan Stanley Senior Funding, Inc. and the lenders party thereto | CoreWeave Financing DDTL V, LLC | Financing | — | — | — | 66 mo | $3.10B | — | Amendedverified | 8-K |
excerptproviding for a $3.1 billion delayed draw term loan facility (the "DDTL 5.0 Facility"). The DDTL 5.0 Facility was entered into primarily to finance capital expenditures required to perform certain customer contracts, including the acquisition of GPU servers and related infrastructure. ... Proceeds from the DDTL 5.0 Facility will support the purchase and deployment of infrastructure dedicated to customer contracts with two large, non-investment grade customersReport an issue with this row | |||||||||||
| Apr 3, 2026 | Briscoe Wind Project Holdings I, LLC; JPM Capital Corporation; Morgan Stanley Wind LLC | Soluna DV Wind SponsorCo, LLC | Other | Briscoe and Floyd counties, Texas | 150 MW | — | — | $53.00M | — | Completedauto 0.9 | 8-K |
excerptThe Briscoe Project Company owns an approximately 149.85 MW nameplate capacity wind generation project located in Briscoe and Floyd counties, Texas (the “Briscoe Project”). ... The aggregate closing payment under the MIPA was approximately $53,000,000.Report an issue with this row | |||||||||||
| Mar 31, 2026 | MUFG Bank, Ltd., Morgan Stanley Asset Funding, Inc., Goldman Sachs Bank USA, JPMorgan Chase Bank, N.A. and the other lenders party to the Credit Agreement | CoreWeave Compute Acquisition Co. VIII, LLC backstop: CoreWeave, Inc. | Financing | — | — | — | 6 yr | $8.50B | — | Amendedverified | 8-K |
excerptproviding for an $8.5 billion delayed draw term loan facility (the "DDTL 4.0 Facility"). The DDTL 4.0 Facility was entered into primarily to finance capital expenditures required to perform a customer contract, including the acquisition of GPU servers and related infrastructure.Report an issue with this row | |||||||||||
Rows marked auto were extracted by a model and not yet reviewed; the excerpt under each row is the verbatim passage the figures came from. Confidence is the extractor's own estimate.