Contract Ledger
Every disclosed AI compute, colocation, hosting, power and equipment contract, one row per disclosure, read from the SEC filing it appeared in. Nulls mean the filing did not say. Nothing is estimated.
Contracts
1
1 from filings
Disclosed value
$2.00B
sum of stated totals, live
Capacity
70 MW
sum of stated MW, live
GPUs
—
where a count was stated
Providers
1
parties delivering
Latest filing
Jun 8, 2026
most recent disclosure
Customer concentration · by provider · filtered
Disclosures · 1
| Filed | Provider | Customer | Kind | Site | MW | GPUs | Term | Total value | Annual | Status | Source |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Jun 8, 2026 | Cipher Stingray LLC | Amazon Data Services, Inc. backstop: Amazon.com, Inc. | Colocation lease | Stingray, Andrews, TX | 70 MW | — | 15 yr | $2.00B | $112.00M | Definitiveverified | 8-K |
excerpt · extension termsCipher Digital has executed a second data center lease with Amazon Data Services, Inc. (“AWS”) for 100 Gross MW / 70 IT MW at its Stingray site ... Purpose-built HPC data center located in Andrews, TX with 70 MW of Critical IT load under contract, with initial rent targeted to start on April 1st, 2027 ... 15 + Three 5-Year Tenant Extension Options ... ~$2.0 - $5.7 Bn Contracted Lease Payments ... 3.0 % Annual Rent Escalator ... Tenant Lease Guarantee: Amazon.com, Inc. (public parent) fully guarantees all base rent and operating expenses Extension: Three 5-year tenant extension options; if all exercised at ceiling rental rate, total contracted lease payments would be approximately $5.7 billion. Report an issue with this row | |||||||||||
Rows marked auto were extracted by a model and not yet reviewed; the excerpt under each row is the verbatim passage the figures came from. Confidence is the extractor's own estimate.