Contract Ledger

Every disclosed AI compute, colocation, hosting, power and equipment contract, one row per disclosure, read from the SEC filing it appeared in. Nulls mean the filing did not say. Nothing is estimated.

Contracts
4
4 from filings
Disclosed value
$5.50B
sum of stated totals, live
Capacity
360 MW
sum of stated MW, live
GPUs
—
where a count was stated
Providers
1
parties delivering
Latest filing
Nov 10, 2025
most recent disclosure
Reset

Customer concentration · by provider · filtered

Akela Data LLC4 contracts
$5.50B · 360 MWtop customer 100%
  • Fluidstack$5.50B

Disclosures · 4

FiledProviderCustomerKindSiteMWGPUsTermTotal valueAnnualStatusSource
Nov 10, 2025Akela Data LLCFluidstack
backstop: Google
Colocation leaseLake Mariner Campus——10 yr——Completedverified8-K
excerpt
In August, Akela executed three ten-year Fluidstack leases, backed by Google, providing 450 MW of capacity and approximately $6.7 billion in contracted revenue. These leases, scheduled to be delivered in phases through 2026, are financed and benefit from Google credit enhancement, creating durable, infrastructure-style cash flows.
Report an issue with this row
Aug 18, 2025Akela Data LLCFluidstack USA I Inc.
backstop: Google LLC
Colocation leaseLake Mariner, NY160 MW—10 yr——Definitiveverified8-K
excerpt · extension terms
On August 17, 2025, TeraWulf Inc. ... announced that its indirect subsidiary Akela Data LLC (“Akela”) had entered into a Datacenter Lease Agreement for colocation building number 5 (“CB-5”) ... with Fluidstack USA I Inc. ... Akela has agreed to lease property at the Company’s Lake Mariner data center campus in upstate New York to Fluidstack ... The CB-5 Premises will provide more than 160 megawatts (MW) of critical IT load ... Akela is expected to complete construction and deliver the CB-5 Premises to Fluidstack by year end 2026. Fluidstack’s obligations to pay rent under the Fluidstack Lease begin on the completion date of the lease and continue for a 10-year term.

Extension: Press release states total contracted revenue has potential to reach $16 billion with lease extensions, but CB-5-specific extension terms are not stated.

Report an issue with this row
Aug 14, 2025Akela Data LLCFluidstack USA I Inc.
backstop: Google LLC
FinancingLake Mariner, NY———$1.80B—Definitiveverified8-K
excerpt
Google will backstop $1.8 billion of Fluidstack's lease obligations to support project-related debt financing and will receive warrants to acquire approximately 41 million shares of TeraWulf common stock
Report an issue with this row
Aug 14, 2025Akela Data LLCFluidstack USA I Inc.
backstop: Google LLC
Colocation leaseLake Mariner, NY200 MW—10 yr$3.70B$370.00MDefinitiveverified8-K
excerpt · extension terms
Akela has agreed to lease property at the Company’s Lake Mariner data center campus in upstate New York to Fluidstack... more than 200 megawatts (MW) of critical IT load... 10-year term. ... approximately $3.7 billion in contracted revenue over the initial 10-year terms and include two five-year extension options which, if exercised, would bring the total contract revenue to approximately $8.7 billion.

Extension: Two five-year extension options, potential total revenue ~$8.7 billion

Report an issue with this row