Contract Ledger
Every disclosed AI compute, colocation, hosting, power and equipment contract, one row per disclosure, read from the SEC filing it appeared in. Nulls mean the filing did not say. Nothing is estimated.
Contracts
2
2 from filings
Disclosed value
$0
sum of stated totals, live
Capacity
408 MW
sum of stated MW, live
GPUs
—
where a count was stated
Providers
1
parties delivering
Latest filing
Feb 26, 2026
most recent disclosure
Customer concentration · by provider · filtered
Disclosures · 2
| Filed | Provider | Customer | Kind | Site | MW | GPUs | Term | Total value | Annual | Status | Source |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Feb 26, 2026 | Abernathy Joint Venture | Undisclosed backstop: Google | Colocation lease | Abernathy HPC Campus, Texas | 168 MW | — | 25 yr | — | — | Definitiveverified | 8-K |
excerptIn October 2025, TeraWulf entered into a joint-venture agreement with Fluidstack to develop the Abernathy HPC Campus in Texas, designed to support 168 critical IT MW under a 25-year lease with annual escalators. ... Construction is progressing with delivery targeted for second half 2026, supported by Google credit enhancement.Report an issue with this row | |||||||||||
| Nov 10, 2025 | Abernathy Joint Venture | Fluidstack backstop: Google | Colocation lease | Abernathy Campus, Texas | 240 MW | — | 25 yr | — | — | Completedverified | 8-K |
excerptThe Abernathy Campus is initially designed for 240 MW of capacity with potential site expansion to 600 MW. The venture, in which TeraWulf holds up to a 51% controlling interest, includes a 25-year lease with Fluidstack, backed by a $1.3 billion Google credit enhancement, and the right to develop future phases leveraging existing transmission infrastructure.Report an issue with this row | |||||||||||
Rows marked auto were extracted by a model and not yet reviewed; the excerpt under each row is the verbatim passage the figures came from. Confidence is the extractor's own estimate.