Contract Ledger
Every disclosed AI compute, colocation, hosting, power and equipment contract, one row per disclosure, read from the SEC filing it appeared in. Nulls mean the filing did not say. Nothing is estimated.
Contracts
1
1 from filings
Disclosed value
$4.00B
sum of stated totals, live
Capacity
150 MW
sum of stated MW, live
GPUs
—
where a count was stated
Providers
1
parties delivering
Latest filing
Jun 2, 2025
most recent disclosure
Customer concentration · by provider · filtered
Disclosures · 1
| Filed | Provider | Customer | Kind | Site | MW | GPUs | Term | Total value | Annual | Status | Source |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Jun 2, 2025 | APLD ELN-03 LLC | CoreWeave, Inc. | Colocation lease | Ellendale Campus, North Dakota (Building 3) | 150 MW | — | 15 yr | $4.00B | — | Definitiveverified | 8-K |
excerpt · extension termsOn May 28, 2025, APLD ELN-02 LLC and APLD ELN-03 LLC ... each entered into a datacenter lease ... with CoreWeave, Inc. ... The second lease is for the full capacity of Building 3, a 150MW data center that is also under construction (“Building 3”) ... The total contract value, for the initial approximately fifteen (15)-year term ... (ii) for the Building 3 Datacenter Lease is expected to be approximately $4 billion Extension: Three 5-year extension options. Report an issue with this row | |||||||||||
Rows marked auto were extracted by a model and not yet reviewed; the excerpt under each row is the verbatim passage the figures came from. Confidence is the extractor's own estimate.