Contract Ledger
Every disclosed AI compute, colocation, hosting, power and equipment contract, one row per disclosure, read from the SEC filing it appeared in. Nulls mean the filing did not say. Nothing is estimated.
Contracts
1
1 from filings
Disclosed value
$4.00B
sum of stated totals, live
Capacity
150 MW
sum of stated MW, live
GPUs
—
where a count was stated
Providers
1
parties delivering
Latest filing
Aug 29, 2025
most recent disclosure
Customer concentration · by provider · filtered
Disclosures · 1
| Filed | Provider | Customer | Kind | Site | MW | GPUs | Term | Total value | Annual | Status | Source |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Aug 29, 2025 | APLD ELN-02 C LLC | CoreWeave, Inc. | Colocation lease | Polaris Forge 1 Campus, Ellendale, North Dakota | 150 MW | — | 15 yr | $4.00B | — | Amendedverified | 8-K |
excerpton August 28, 2025, APLD ELN-02 C LLC, a subsidiary of the Company, ... Forge 1 (“Building 4”), a 150MW data center to be constructed by the Company. ... The total contract value for the initial approximately fifteen (15)-year term of the Building 4 Lease is expected to be approximately $4.0 billion.Report an issue with this row | |||||||||||
Rows marked auto were extracted by a model and not yet reviewed; the excerpt under each row is the verbatim passage the figures came from. Confidence is the extractor's own estimate.