Contract Ledger

Every disclosed AI compute, colocation, hosting, power and equipment contract, one row per disclosure, read from the SEC filing it appeared in. Nulls mean the filing did not say. Nothing is estimated.

Contracts
9
9 from filings
Disclosed value
$467.00B
sum of stated totals, live
Capacity
7.25 GW
sum of stated MW, live
GPUs
—
where a count was stated
Providers
5
parties delivering
Latest filing
Aug 17, 2026
most recent disclosure
Reset

Customer concentration · by provider · top 8

Microsoft1 contract
$250.00B · —top customer 100%
  • OpenAI$250.00B
AWS2 contracts
$200.00B · 2.00 GWtop customer 100%
  • OpenAI$200.00B
CoreWeave4 contracts
$17.00B · —top customer 100%
  • OpenAI$17.00B
SB Energy Corp.1 contract
— · 4.25 GWtop customer 100%
  • OpenAI (affiliate of OpenAI Group PBC)4.25 GW
— · 1.00 GWtop customer 100%
  • OpenAI1.00 GW

Disclosures · 9

FiledProviderCustomerKindSiteMWGPUsTermTotal valueAnnualStatusSource
Aug 17, 2026SB Energy Corp.OpenAI (affiliate of OpenAI Group PBC)Colocation leasePORTS-Pike Technology Campus (Portsmouth Site), Pike County, Ohio4.25 GW—20 yr——Amendedverified8-K
excerpt · extension terms
SB Energy will build, own and operate the data center under a 20-year lease to OpenAI. ... OpenAI will utilize the capacity at the site. The AI factory will use NVIDIA's full-stack DSX AI factory platform, including GPUs, CPUs and networking. The initial deployment is designed to support 4.25 IT-GW of AI factory capacity.

Extension: NVIDIA has the option to extend the opportunity at PORTS-Pike beyond the initial 4.25 IT-GW; OpenAI will be the customer for 8 IT-GW total.

Report an issue with this row
Apr 9, 2026AWSOpenAIGPU cloud capacity————$100.00B—Completedverified8-K
excerpt
We have customer commitments that make our capex investments predictable. We're not investing approximately $200 billion in capex in 2026 on a hunch. The recent OpenAI commitment (over $100 billion) is an example of this, but there are several other customer agreements completed (and unannounced), or deep in process.
Report an issue with this row
Feb 27, 2026AWSOpenAIGPU cloud capacity—2.00 GW—8 yr$100.00B$12.50BExpandedverified8-K
excerpt
OpenAI and AWS are expanding their existing $38 billion multi-year agreement by $100 billion over 8 years. The expansion includes OpenAI committing to consume approximately 2 gigawatts of Trainium capacity through AWS infrastructure, which will support demand for Stateful Runtime, Frontier, and other advanced workloads.
Report an issue with this row
Oct 29, 2025MicrosoftOpenAIGPU cloud capacity————$250.00B—Amendedverified8-K
excerpt
we've signed a new definitive agreement that builds on our foundation, strengthens our partnership, and sets the stage for long-term success for both organizations. ... OpenAI has contracted to purchase an incremental $250B of Azure services, and Microsoft will no longer have a right of first refusal to be OpenAI's compute provider.
Report an issue with this row
Oct 15, 2025CoreWeaveOpenAIPower supply————$6.50B—Expandedverified8-K
excerpt
CoreWeave Expands Agreement with OpenAI by up to $6.5B (September 25, 2025)
Report an issue with this row
Oct 6, 2025Advanced Micro Devices, Inc.OpenAIEquipment purchase—1.00 GW————Amendedverified8-K
excerpt
Concurrent with signing, Warrantholder agreed to a binding commitment to purchase (directly or through its affiliates or Authorized Purchasers) the initial one (1) gigawatt of AMD Instinct MI450 Series GPU products. ... agreement to power OpenAI's next-generation AI infrastructure across multiple generations of AMD Instinct GPUs. ... Our partnership with OpenAI is expected to deliver tens of billions of dollars in revenue for AMD while accelerating OpenAI's AI
Report an issue with this row
Oct 2, 2025CoreWeave, Inc.OpenAI OpCo, LLCGPU cloud capacity——————Amendedverified8-K
excerpt
"Fifth Amendment OpenAI Contract" shall mean that certain CoreWeave Reserved Compute Instance Order Form #2 dated May 8, 2025 by and between CoreWeave, Inc. and OpenAI OpCo, LLC (including as amended by that certain Amendment No. 1 dated as of June 25, 2025).
Report an issue with this row
Sep 25, 2025CoreWeave, Inc.OpenAI OpCo, LLCGPU cloud capacity————$6.50B—Definitiveverified8-K
excerpt
On September 23, 2025, CoreWeave, Inc. (the “Company”) and OpenAI OpCo, LLC (“OpenAI”) entered into a new order form (the “Order Form”) under the existing Master Services Agreement (“MSA”) dated as of May 8, 2025, pursuant to which the Company provides OpenAI access to cloud computing capacity through fulfillment of reserved capacity orders submitted to the Company by OpenAI and as may be amended upon the Company’s and OpenAI’s mutual agreement. Subject to any termination described below and satisfaction of delivery and availability of service requirements, OpenAI has committed to pay the Company up to approximately $6.5 billion through May 31, 2031 under the Order Form.
Report an issue with this row
Aug 12, 2025CoreWeave, Inc.OpenAIGPU cloud capacity————$4.00B—Expandedverified8-K
excerpt
◦ $4 billion expansion deal with OpenAI, in addition to previously announced $11.9 billion deal
Report an issue with this row

Rows marked auto were extracted by a model and not yet reviewed; the excerpt under each row is the verbatim passage the figures came from. Confidence is the extractor's own estimate.