4
4 from filings
Disclosed value
$775.00M
sum of stated totals, live
Capacity
1.21 GW
sum of stated MW, live
GPUs
—
where a count was stated
Providers
4
parties delivering
Latest filing
Jul 17, 2026
most recent disclosure
Reset

Customer concentration · by provider · top 8

the Lenders1 contract
$775.00M · —top customer 100%
  • Nebius Compute II, LLC and Nebius Compute II Oy$775.00M
— · 5 MWtop customer 100%
  • Nebius Group N.V.5 MW
Nebius1 contract
— · —
    — · —
    • Nebius1×

    Disclosures · 4

    FiledProviderCustomerKindSiteMWGPUsTermTotal valueAnnualStatusSource
    Jul 17, 2026the LendersNebius Compute II, LLC and Nebius Compute II Oy
    backstop: Nebius Group N.V.
    Financing————$775.00M—Amendedverified6-K
    excerpt
    The Facility Agreement provides for a senior secured term loan facility in an aggregate principal amount of approximately $775 million. ... The maturity date of the Facility Agreement is October 31, 2030.
    Report an issue with this row
    May 13, 2026NebiusNebius Group N.V.Power supplyPennsylvania1.20 GW————Expandedverified6-K
    excerpt
    we are announcing a new site in Pennsylvania where we have secured power for a deployment of up to 1.2 GW.
    Report an issue with this row
    Nov 19, 2024unnamed colocation providerNebius Group N.V.Colocation leaseKansas City, MO5 MW————Expandedverified6-K
    excerpt
    Scheduled to go live in Q1 2025, the Kansas City cluster will house thousands of state-of-the-art NVIDIA GPUs, primarily H200 Tensor Core GPUs in the initial phase, with the energy-efficient NVIDIA Blackwell platform expected to arrive in 2025. The colocation can be expanded from an initial 5 MW up to 40 MW, or about 35 thousand GPUs, at full potential capacity.
    Report an issue with this row
    Oct 18, 2024colocation data center providerNebiusColocation leaseParis, France—————Amendedverified6-K
    excerpt
    Energy-efficient own data center in Finland , colocation data center in Paris 3 and further expansion plans ... (3) Agreement signed in July 2024, new capacity in Paris, France to be put into operation by the end of November 2024.