Every disclosed AI compute, colocation, hosting, power and equipment contract, one row per disclosure, read from the SEC filing it appeared in. Nulls mean the filing did not say. Nothing is estimated.

Contracts
5
5 from filings
Disclosed value
$44.50B
sum of stated totals, live
Capacity
200 MW
sum of stated MW, live
GPUs
—
where a count was stated
Providers
3
parties delivering
Latest filing
Feb 12, 2026
most recent disclosure
Reset

Customer concentration · by provider · top 8

Nebius3 contracts
$34.80B · —top customer 100%
  • Microsoft$34.80B
$9.70B · 200 MWtop customer 100%
  • Microsoft Corporation$9.70B
CoreWeave, Inc.1 contract
— · —
  • Microsoft Corporation1×

Disclosures · 5

FiledProviderCustomerKindSiteMWGPUsTermTotal valueAnnualStatusSource
Feb 12, 2026NebiusMicrosoftGPU cloud capacity——————Amendedverified6-K
excerpt
Nebius has amended its agreement with Microsoft to add 1.2 GW of additional capacity in the United States. ... Under the amended agreement, Microsoft will prepay an aggregate of $2.2 billion for the additional capacity.
Report an issue with this row
Nov 13, 2025Nebius, Inc.MicrosoftGPU cloud capacityVineland, New Jersey——5 yr$17.40B—Amendedverified6-K
excerpt · extension terms
On September 8, 2025, Nebius, Inc., a wholly owned subsidiary of the Company, entered into a commercial agreement (the "Agreement") with Microsoft, pursuant to which Nebius Inc. will provide Microsoft access to dedicated GPU infrastructure capacity in clusters (each, a "GPU Service") at its new data center in Vineland, New Jersey over a five-year term. ... Microsoft has committed to pay the Company fees under the Agreement estimated to be up to $17.4 billion through 2031.

Extension: Microsoft may acquire additional services and/or capacity under the Agreement.

Report an issue with this row
Nov 3, 2025IE US Hardware 3 Inc.Microsoft CorporationGPU cloud capacityHorizon 1-4 data center facilities, Childress, Texas200 MW——$9.70B—Amendedverified8-K
excerpt
The total contract value is approximately $9.7 billion through 2031, with 20% of the contract value for each tranche to be paid prior to the applicable delivery date and credited against the service fees due and payable after the 24 th calendar month of the applicable GPU Service term on a pro rata basis. ... The GPU Services will comprise NVIDIA GB300 GPUs and will be installed across four data center facilities at Childress known as “Horizon 1,” “Horizon 2,” “Horizon 3,” and “Horizon 4”, representing a combined IT load of approximately 200MW.
Report an issue with this row
Oct 2, 2025CoreWeave, Inc.Microsoft CorporationGPU cloud capacity——————Amendedverified8-K
excerpt
"Fifth Amendment Albatross Contract" shall mean that certain CoreWeave Reserved Compute Instance Order Form 7 dated August 6, 2025 by and between CoreWeave, Inc. and Microsoft Corporation, as amended in accordance with this Agreement.
Report an issue with this row
Sep 8, 2025Nebius, Inc.MicrosoftGPU cloud capacityVineland, New Jersey——5 yr$17.40B—Amendedverified6-K
excerpt
On September 8, 2025, Nebius, Inc. (the "Company"), a wholly owned subsidiary of Nebius Group N.V. ("Nebius Group"), entered into a commercial agreement (the "Agreement") with Microsoft, pursuant to which the Company will provide Microsoft access to dedicated GPU infrastructure capacity in tranches (each, a "GPU Service") at its new data center in Vineland, New Jersey (the "Data Center") over a five-year term. ... Subject to the satisfaction of the deployment and availability of the GPU Services, the total contract value is about $17.4 billion through 2031. Microsoft may also acquire additional services and/or capacity under the Agreement, which would increase the total contract value to about $19.4 billion.
Report an issue with this row

Rows marked auto were extracted by a model and not yet reviewed; the excerpt under each row is the verbatim passage the figures came from. Confidence is the extractor's own estimate.