Bitdeer Technologies

BTDRpublic
crypto-blockchainSGbitdeer.com$11.66

Backers

No backer on file. That means no tracked fund's portfolio or Form D names this company — not that it is unbacked.

Contracts as provider

5 disclosures · 196 MW · $10.20B
FiledCustomerKindSiteMWGPUsTermTotalStatusSource
Sep 16, 2026VoltaGPU cloud capacityTydal, Norway Campus——16 yr$4.70BAmendedauto6-K
excerpt · extension terms
Bitdeer announced a 16-Year AI/HPC Data Center Lease for its Tydal, Norway Campus, representing approximately $4.7 billion of total contract value over the initial base term, with the potential to reach a total contract value of approximately $8.0 billion if the tenant exercises its one-time 8-year lease extension. ... $4.7B, 16-Year Lease with Volta at Tydal, Norway

Extension: One-time 8-year lease extension; potential total contract value ~$8.0B if exercised.

Report an issue with this row
Sep 16, 2026UndisclosedGPU cloud capacityA202, Johor Campus, Malaysia65 MW—10 yr—Amendedauto6-K
excerpt
Bitdeer AI executed a 10-year data center services agreement securing an additional 65.1 MW at its A202 facility on the Johor campus, scaling total campus AI Cloud capacity to 86.8 MW to capture high-density compute demand.
Report an issue with this row
Sep 16, 2026UndisclosedGPU cloud capacityA102, Malaysia10 MW——$800.00MAmendedauto6-K
excerpt
Bitdeer AI secured 100% contracted GPU capacity for its 9.5 MW A102 facility in Malaysia ahead of energization through long-term commitments, representing more than $800 million in total expected revenue.
Report an issue with this row
Aug 26, 2026subsidiary of VoltaColocation leaseTydal, Norway121 MW—16 yr$4.70BExpandedverified6-K
excerpt · extension terms
Approximately $4.7 billion in contracted revenue over the initial 16-year base-term, with the potential to reach a total contract value of $8.0 billion through a one-time 8-year lease extension. ... Tenant is a subsidiary of Volta; the entire 121 IT MW will be configured to run NVIDIA GPUs for the end customer, a leading AI lab. Credit backstop is anticipated to be arranged by affiliates of two leading top-tier global financial institutions via Letters of Credit, totaling approximately $1.3 billion and subject to customary conditions.

Extension: Potential total contract value of $8.0 billion through a one-time 8-year lease extension.

Report an issue with this row
Jul 21, 2026UndisclosedGPU cloud capacity——25 yr—Definitiveverified6-K
excerpt
GB300 Customer Delivery: 5-year GPU cloud sales contract executed and successfully completed customer deliveries following the deployment and production launch of 2 units of NVIDIA GB300 NVL72 clusters
Report an issue with this row

Concentration over time

3 filing dates
As ofContractsValueTop customerTop share
Jul 21, 202610 MWUndisclosed—
Aug 26, 20262$4.70Bsubsidiary of Volta100%
Sep 16, 20265$10.20Bsubsidiary of Volta46%

Contracts as customer

9 disclosures · 2.08 GW
FiledProviderKindSiteMWGPUsTermTotalStatusSource
Sep 16, 2026unaffiliated third-party supplierEquipment purchaseA201, Malaysia—133——Amendedauto6-K
excerpt
Bitdeer AI advanced hardware readiness for its A201 facility by procuring 133 racks of GB300 ahead of energization at market price from an unaffiliated third-party supplier, ensuring seamless post-energization deployment and rapid time-to-market.
Report an issue with this row
Jul 21, 2026Tydal, Norway lease counterpartyColocation leaseTydal, Norway50 MW———Definitiveauto6-K
excerpt
Tydal, Norway lease has been executed, subject to certain conditions precedent ... Tydal, Norway – phase 1: 50 MW, Q4 '26, Crypto to Colocation
Report an issue with this row
Jul 21, 2026Malaysia data center lessorColocation leaseJohor Bahru, Malaysia22 MW12810 yr—Definitiveverified6-K
excerpt
10-year lease agreement signed for new data center in Malaysia to provide 21.7 IT MW of capacity, with handover to Bitdeer expected Q1 2027. Facility planned to support deployment of 128 NVIDIA GB300 NVL72 systems.
Report an issue with this row
May 12, 2026unnamed lessorColocation leaseCyberjaya, Malaysia2 MW———Expandedauto6-K
excerpt
Capacity under lease arrangement
Report an issue with this row
May 12, 2026unnamed vendorEquipment purchaseMalaysia and US—18——Expandedverified6-K
excerpt
Recent deployments include: 2 units of GB300 delivered to our leased Malaysia datacenter at the end of April and 16 units of B300 delivered in the US in early May.
Report an issue with this row
Jan 12, 2026a local utility companyPower supplyNiles, Ohio300 MW———Expandedauto6-K
excerpt
Niles, Ohio – 300 MW grid-interconnected development site, with target energization date of Q4 2028. The project includes 41.8 acres of owned land and a transmission line extension agreement with a local utility company.
Report an issue with this row
Oct 15, 2025local utilityPower supplyClarington, Ohio570 MW———Amendedauto6-K
excerpt
Clarington, Ohio – 570 MW under contract with local utility and will be available by end of Q3 2026. Power and data center infrastructure to be completed in Q2 2027.
Report an issue with this row
Aug 19, 2025AEP OhioPower supplyClarington, Ohio570 MW———LOIauto6-K
excerpt
In July, we achieved a key milestone by signing the Letter of Agreement with AEP Ohio for the second phase of Clarington, advancing the final stages for the full 570 MW of capacity.
Report an issue with this row
Jul 5, 2024Monroe County Port AuthorityPower supplyOhio, U.S.570 MW—30 yr—Amendedauto6-K
excerpt
We entered into a 30-year lease agreement with Monroe County Port Authority for 570 MW of ready-to-use power infrastructure.
Report an issue with this row

Signals

No filings, rounds or news on file for this company.